Key takeaways
- The main large formats
- 587/588 Ah: about 1.88 kWh and 10–10.6 kg per cell; 628 Ah: about 2.01 kWh and 11.3 kg; for comparison 314 Ah: about 1.0 kWh and 5.5–5.6 kg
- System capacity
- A 20-ft container goes from about 5 MWh with 314 Ah cells to about 6.25 MWh with 587 Ah and about 6.9 MWh with 628 Ah and above
- Market timing
- In the first half of 2026, cells of 500 Ah and above passed one tenth of utility-scale storage cell shipments and are rising fast; 314 Ah is still the volume format
- Impact on the line
- Cell weight roughly doubles and 0.5P current rises from 157 A to about 294 A; at the same 8 PPM, energy output goes from about 482 kWh to about 902 kWh an hour
- Retrofit or new line
- Retrofit when the module fits the existing envelope and robots and presses have headroom; otherwise build new or redesign the key stations for large cells
Where do large cells stand today?
From mid-2025, leading cell makers began mass-producing storage cells of 500 Ah and above. By the first half of 2026 these cells had passed one tenth of utility-scale storage cell shipments, and the industry expects that share to keep rising this year. 314 Ah is still the largest-volume format, in tight supply, with prices up more than 15 % in six months.
Typical figures for common formats (dimensions vary a little between makers; the cell datasheet rules):
| Format | Energy per cell | Weight | Size (approx.) | 20-ft container |
|---|---|---|---|---|
| 314 Ah | 1.00 kWh | 5.5–5.6 kg | 72 × 174 × 207 mm | about 5 MWh |
| 587 / 588 Ah | 1.88 kWh | 10–10.6 kg | 72–74 × 274–310 × 214–222 mm | about 6.25 MWh |
| 628 Ah | 2.01 kWh | about 11.3 kg | 72 × 352 × 205 mm | about 6.9 MWh |
| 684 Ah (stacked) | about 2.19 kWh | — | — | about 6.9 MWh |
| 1000 Ah and above | over 3 kWh | from about 20 kg | over 500 mm long | larger systems |
The big win is at system level: more energy in the same container, with fewer parts, connections and integration steps. A 628 Ah cell, for example, is about as wide as two 314 Ah cells side by side, so some PACK structures carry over.
Which stations change with large cells?
Following the station order of the 8 PPM line on this site:
| Station | From 314 Ah to 500 Ah-plus | What to do |
|---|---|---|
| Depalletizing and infeed | Cell weight rises from about 5.6 kg to 10–11 kg | New grippers and tray locating; check robot payload — five cells per pick go from about 28 kg to about 53 kg |
| Scan / OCV test | Larger cell, lower internal resistance | New test fixtures and probe positions; confirm IR range and resolution cover the large cell |
| Stacking and pressing | Face area about 1.7× larger | At the same face pressure, press force is about 1.7× higher; check press stroke and fixture width |
| Terminal addressing | Terminal positions and pitch change | Update vision programs and recipes; positioning accuracy stays the same |
| Busbar welding | Larger busbar section, cell current about doubles | Re-qualify weld parameters (penetration, width, pull), raising laser power or changing the spot if needed |
| Module EOL | Higher operating current | Confirm current ranges for DC resistance and similar tests; new contact fixtures |
| Conveyor and module handling | Heavier, wider modules | Check pallet-conveyor load rating and pallet size |
| PACK assembly and test | Structures, cooling plates and harnesses change | New assembly fixtures; leak-test and EOL fixtures follow |
One change is easy to miss: the number of welds. With two terminals per cell, 314 Ah needs about 1,990 welds per MWh and 587 Ah only about 1,065 — about 46 % fewer. Fewer welds raise the bar for each one, since each carries more current.
How do takt and output change?
At the same takt in cells per minute, large cells nearly double the energy output:
| Cell | Energy per hour at 8 PPM | Annual output (20 h × 300 days × 85 % OEE) |
|---|---|---|
| 314 Ah | about 482 kWh | about 2.46 GWh |
| 587 Ah | about 902 kWh | about 4.60 GWh |
| 628 Ah | about 965 kWh | about 4.92 GWh |
Re-check the real takt for the large cell: weight- and size-driven moves such as handling and pressing may slow down, while welding may speed up because there are fewer welds. For the method, see PPM to GWh: line capacity.
Retrofit the existing line or build new?
A retrofit is worth considering when:
- the large-cell module still fits the line’s envelope (the 8 PPM line on this site takes modules of H 100–240 mm, W 150–370 mm and L 300–1000 mm; 587, 588 and 628 Ah cells fit in height and width, and module length depends on the series count);
- robot payload, press force and conveyor load have enough headroom;
- the changes are mainly grippers, fixtures, tooling and programs.
Build new, or redesign the key stations, when:
- cell length or weight is outside the line’s range (cells above 1000 Ah, for example);
- robots, presses or testers have no headroom and the retrofit costs approach new equipment;
- you also want a big step up in takt or automation, and the retrofit is the moment to do it.
Start with a compatibility review: take the target cell’s datasheet and the module and PACK drawings, and check size, weight, force and current station by station.
A flexible line for both 314 Ah and large cells
- Pick a main format. Running several cell formats in one plant cuts utilisation noticeably through changeover losses. Set the main format from your order book and cover the rest.
- Put changeover times in the contract. Target times for swapping grippers, fixtures and welding tooling, and the first-article procedure, belong in the technical agreement.
- Modular tooling. Quick-change fixtures and test tooling, with recipes sent from MES, cut setup errors.
- Size key equipment for the large cell. Choose robots, presses, lasers and EOL testers for the large-cell maximum; the small cell is then covered.
What we can supply
The 8 PPM line on this site is designed around the 314 Ah cell with 587 Ah compatibility built in. For 628 Ah, 684 Ah and cells above 1000 Ah, we can supply complete lines or single machines through our supply-chain service, and review an existing line’s compatibility with a retrofit plan.
Questions buyers ask
01Can an existing 314 Ah line simply run 587 Ah cells?
Not as is. At a minimum the infeed grippers, stacking fixtures, welding tooling and test fixtures change, and robot payload, press force, conveyor load and EOL test current ranges must be checked. If the line was designed with large cells in mind (as the 8 PPM line on this site was), the changes are much smaller.
02Does takt drop with large cells?
It depends on the station. Heavier, larger cells can slow handling and stacking moves, but each cell carries nearly twice the energy, so even if takt in cells per minute dips a little, output in GWh usually rises clearly. Re-check the takt station by station for the large cell.
03Can one line handle both 314 Ah and 587 Ah?
Yes, as a flexible line, at the cost of more tooling, more complex changeovers and higher up-front investment. Running several cell formats in one plant cuts equipment utilisation noticeably, so pick the main format from your order book and cover the others with fast changeovers.
04What about cells above 1000 Ah?
Cells above 1000 Ah can be over 500 mm long and weigh around 20 kg, beyond the size and handling range of most module and PACK lines; they usually need a purpose-built line. We can supply such lines through our supply-chain service.
Related pages
Prices, takt figures and parameters here are typical industry ranges for early planning and comparison; your configuration and quote come from a project proposal.