Guides

How to Choose a Battery Pack Assembly Line Supplier in China (RFQ Checklist)

How to choose a battery pack assembly line supplier in China: the RFQ checklist, and a table of the 8 PPM and 12–15 PPM figures already published on this site.

Key takeaways

What to freeze first
Cell format and size, module and PACK envelope, takt in cells per minute, which stations are automatic, and the end-of-line tests
Two published lines
8 PPM (7.5 s per cell, 55 × 9 × 3.5 m, 250 kW, from RMB 2 million) and 12–15 PPM (56 × 10 × 4 m, 300 kW, quoted to the plant)
Acceptance
Factory acceptance in Wuhan before crating, against numbers in the contract; site acceptance after installation on your utilities
Traceability
On the line described here, pass limits come from MES and each module’s test data ties back to the cells’ barcodes
Where the numbers come from
Only the datasheet, equipment pages and guides already on this site. No figure is taken from an unopened workbook

Updated · Written by the Stratavolt applications team, checked by an engineer before publication · Editorial standards

How to choose a battery pack assembly line supplier in China?

Choose a supplier by freezing the cell, module and PACK size, takt, stations, end-of-line tests, traceability, and factory and site acceptance in the request before you compare prices. The 8 PPM and 12–15 PPM lines published on this site are the worked example.

Price comes after that list. A quote that does not say which of those items it includes cannot be compared with one that does. The cost guide makes the same point: quotes for a similar yearly output differ because some cover only assembly stations and others add cell sorting, end-of-line and leak testing, logistics and MES.

What to put in the RFQ

Use the headings this site already publishes. Each one links to the page that holds the detail.

RFQ heading What to attach Where it is published here
Cell format Datasheet: chemistry, ampere-hours, and height, width and thickness with tolerance The reference cell is 314 Ah, 207 × 173 × 72 mm, ±0.5 mm, with 587 Ah compatibility planned. Datasheet
Module and PACK size Drawings, series-parallel layout (the reference module is 1P13S), and the envelope the line must accept Module 100–240 mm high, 150–370 mm wide, 300–1000 mm long. PACK 100–250 × 300–800 × 600–1200 mm. Datasheet
Target PPM Cells per minute, hours per day, days per year, and the OEE you want the yearly figure to use 8 PPM or 15 PPM and the configurator
Stations Which of the process steps are automatic, semi-automatic or manual 21 stations on the 8 PPM line
A single station’s limits The numbers you will accept, not a brochure range The busbar welder, for example, is 6 kW, 50–100 mm/s, penetration ≥ 1.0 mm, width ≥ 1.5 mm, pull-out ≥ 1000 N. Welding station
End-of-line tests Insulation, withstand, voltage, resistance, BMS, relays, and leak tests, each with a limit EOL guide. On this 8 PPM line, module insulation is DC 1000 V and ≥ 500 MΩ; withstand is DC 2800 V and leakage ≤ 10 mA
Traceability Barcode, what is stored against it, and who may change a pass limit The EOL guide: limits come from MES, and each module’s results trace to every cell in it
Factory and site acceptance The checks, the numbers, and whether you attend or watch on video Factory acceptance checklist and site acceptance checklist
Payment Deposit, the payment after factory acceptance, retention after commissioning, or a letter of credit Payment terms. The cost guide records a 30/30/30/10 split as common in China; the payment page agrees the split per project

Example: two line specs

Every cell below is already published on this site. The 8 PPM column is the line in the datasheet and the 8 PPM vs 15 PPM guide. The 12–15 PPM column is from that same guide. Where this site does not publish a figure, the cell says so. Nothing here is filled from an unopened parameter workbook.

8 PPM line 12–15 PPM line
Takt 8 cells per minute (7.5 s per cell). A 1P13S module is about every 97.5 s 12–15 cells per minute (4–5 s per cell). A 1P13S module is about every 52 s at 15 PPM
Reference cell 314 Ah prismatic, 207 × 173 × 72 mm, ±0.5 mm; 587 Ah compatibility planned 314 Ah prismatic. A 587 Ah note is not published for this line
Yearly output, 314 Ah, 20 h, 300 days, 85% OEE About 2.46 GWh About 3.69 GWh at 12 PPM, about 4.61 GWh at 15 PPM
Same basis, 8 h a day About 0.98 GWh About 1.48 GWh at 12 PPM, about 1.84 GWh at 15 PPM
Pass rate ≥ 99% (equipment-caused defects only) ≥ 99%
Operators per shift About 21: 3 in cell processing, 6 in module stacking and welding, 12 in PACK 19–21: cell processing and stacking 4, module welding 3, PACK 12–14
Stations 21, in three segments A station count is not published for this line
Module envelope 100–240 mm high, 150–370 mm wide, 300–1000 mm long Not published as its own envelope
PACK envelope 100–250 mm high, 300–800 mm wide, 600–1200 mm long Not published as its own envelope
Footprint (L × W × H) 55 × 9 × 3.5 m, excluding warehouse and aisles 56 × 10 × 4 m, excluding warehouse and aisles
Power 3-phase 5-wire 380 V ±5%, 50 Hz, 250 kW rated 3-phase 5-wire 380 V ±5%, 50 Hz, 300 kW rated
Compressed air 0.5–0.7 MPa, at least 3,000 L/min 0.5–0.7 MPa, 5,500 L/min
Nitrogen 0.5 MPa, 40 L/min 0.5 MPa, 40–80 L/min
Floor loading ≥ 800 kg/m² ≥ 800 kg/m²
Module EOL settings DC 1000 V, ≥ 500 MΩ; withstand DC 2800 V, leakage ≤ 10 mA Not published as station settings for this line
Starting price From RMB 2 million for the base configuration No starting price is published. The line is quoted to your cell, module and plant

Staffing is a planning figure: the split between sections is adjusted to the plant and the shift pattern.

The English parameter sheets for these two lines were opened on 10 November 2026. They match the columns above. The 8 PPM sheet names the line, 8 PPM on a 1P13S reference, 314 Ah with 587 Ah planned, a pass rate of at least 99% for equipment-related defects, 55 × 9 × 3.5 m, 380 V ±5% at 50 Hz and 250 kW, air of at least 3,000 L/min, nitrogen at 40 L/min, and a floor of at least 800 kg/m². The 12–15 PPM sheet, which excludes container assembly, names 12–15 PPM on a 1P13S reference, 314 Ah cells, about 1–2 GWh a year on 300 days and 8 hours, a pass rate of at least 99%, 4 operators in cell processing and stacking, 3 in module welding and 12–14 in PACK assembly, 56 × 10 × 4 m, 300 kW, 5,500 L/min of air, 40–80 L/min of nitrogen, and the same floor load. No figure on either sheet replaces a number already in the table. The sheets do not publish a station count, a module or PACK envelope, or a starting price for the faster line.

What a line specification covers

A specification, as this site already splits it, covers eight groups. They are the same groups as the RFQ table above: the cell, the module and PACK, the takt and the yearly basis, the station list, each station’s limits, the end-of-line and leak tests, traceability, the plant utilities (power, air, nitrogen, floor, footprint), and the factory and site acceptance together with the payment split. If a quote is silent on one group, ask for that group before you use the price.

What to do with the two lines

The 8 PPM vs 15 PPM guide says to choose 8 PPM when the plan is up to about 2.5 GWh a year on two shifts, and 12–15 PPM when the plan needs 3.5 GWh or more, or about 1.5–1.8 GWh from a single shift. Try other hours and OEE values in the configurator. The compressed-air step from at least 3,000 L/min to 5,500 L/min, and the extra 50 kW, have to fit the building.

Acceptance before you pay the balance

The wider sequence, from the company check to site acceptance, is how to buy a production line from China safely. Factory acceptance runs in Wuhan before crating, against the checklist in the contract, with your cells where possible. You attend or watch on video. The Excel checklist is the blank to adapt. Site acceptance follows installation.

Send the cell datasheet, the module drawing and the target output through the contact form, or email sales@zerolineai.com. The reply is a configuration against the list above.

Questions buyers ask

01

How do I choose a battery pack assembly line supplier in China?

Freeze the cell, the module and PACK size, the takt, the stations, the end-of-line tests, traceability, and factory and site acceptance in the request before you compare prices. Then read the two lines this site already publishes, 8 PPM and 12–15 PPM, against that list. Ask for the factory acceptance in Wuhan, on video if you cannot travel, before anything is crated.

02

What should a battery pack line RFQ include?

The cell datasheet, module and PACK drawings, target output and shift pattern, which stations must be automatic, the end-of-line and leak-test items with their limits, how barcodes and MES trace each cell, the factory and site acceptance checks, and the payment split. The 8 PPM line on this site starts at RMB 2 million in its base configuration; a 12–15 PPM line has no published starting price.

03

What is the difference between the 8 PPM and 15 PPM lines on this site?

8 PPM is one cell every 7.5 seconds, about 2.46 GWh a year at 20 hours, 300 days and 85% OEE with 314 Ah cells, in 55 × 9 × 3.5 m at 250 kW. 12–15 PPM is one cell every 4–5 seconds, about 3.69–4.61 GWh on the same basis, in 56 × 10 × 4 m at 300 kW. The 8 PPM line runs with about 21 operators per shift and the 12–15 PPM line with 19–21; both are specified at a pass rate of at least 99% for equipment-caused defects.

Related pages

Prices, takt figures and parameters here are typical industry ranges for early planning and comparison; your configuration and quote come from a project proposal.