Guides

8 PPM or 15 PPM: which ESS module and PACK line capacity do you need?

Side-by-side specifications of an 8 PPM and a 12–15 PPM prismatic ESS module and PACK line — capacity, staffing, footprint, power, air and nitrogen — and how to choose between them.

Key takeaways

Capacity
With 314 Ah cells, 20 h a day, 300 days and 85 % OEE: about 2.5 GWh a year at 8 PPM and 3.7–4.6 GWh at 12–15 PPM. On one 8-hour shift: about 1 GWh and 1.5–1.8 GWh.
Staffing
The 8 PPM line runs with about 21 operators per shift, the 12–15 PPM line with 19–21. The faster line needs 7 people before PACK instead of 9 and puts 12–14 in PACK assembly.
Footprint and power
8 PPM: 55 × 9 × 3.5 m, 250 kW. 12–15 PPM: 56 × 10 × 4 m, 300 kW. Both need a floor rated for at least 800 kg/m².
Utilities that grow most
Compressed air rises from at least 3,000 L/min to 5,500 L/min, and nitrogen from 40 L/min to 40–80 L/min, both at the same pressures.
How to choose
Below about 2.5 GWh a year of planned output on two shifts, the 8 PPM line is enough and costs less. Choose 12–15 PPM when the plan needs 3.5 GWh or more, or the same output on a single shift.

Updated · Written by the Stratavolt applications team, checked by an engineer before publication · Editorial standards

Two lines side by side

Both lines assemble prismatic LFP cells into energy-storage modules and packs, with a 1P13S module as the design reference. Takt is counted in cells per minute (PPM). The figures are from the two lines’ specification sheets; the faster line’s sheet excludes the container assembly section.

8 PPM line 12–15 PPM line
Takt 8 cells per minute (7.5 s per cell) 12–15 cells per minute (4–5 s per cell)
Reference cell 314 Ah prismatic; 587 Ah compatibility planned 314 Ah prismatic
Pass rate ≥ 99 % (equipment-caused defects only) ≥ 99 %
Operators per shift About 21: cell processing 3, module stacking and welding 6, PACK about 12 19–21: cell processing and stacking 4, module welding 3, PACK 12–14
Footprint (L × W × H) 55 × 9 × 3.5 m 56 × 10 × 4 m
Power 3-phase 5-wire 380 V ±5 %, 50 Hz, 250 kW rated 3-phase 5-wire 380 V ±5 %, 50 Hz, 300 kW rated
Compressed air 0.5–0.7 MPa, at least 3,000 L/min 0.5–0.7 MPa, 5,500 L/min
Nitrogen 0.5 MPa, 40 L/min 0.5 MPa, 40–80 L/min
Floor loading ≥ 800 kg/m² ≥ 800 kg/m²

Footprints exclude the warehouse and logistics aisles. Staffing is a planning figure: the split between sections is adjusted to the plant and the shift pattern.

How much does each line produce in a year?

Annual output = takt × 60 × hours per day × days per year × OEE × cell energy. A 314 Ah LFP cell holds about 1.005 kWh. The formula and quick tables are in PPM to GWh.

Basis 8 PPM 12 PPM 15 PPM
20 h a day, 300 days, 85 % OEE about 2.46 GWh about 3.69 GWh about 4.61 GWh
8 h a day, 300 days, 85 % OEE about 0.98 GWh about 1.48 GWh about 1.84 GWh

The faster line’s specification sheet states 1–2 GWh a year on 8 hours a day and 300 days, which matches the single-shift row.

Which line should you choose?

  • Choose 8 PPM when the plan is up to about 2.5 GWh a year on two shifts, the budget is tight, or the market is still being proven. It needs less power, air and floor, and the base configuration starts at RMB 2 million.
  • Choose 12–15 PPM when the plan needs 3.5 GWh or more, or when you want about 1.5–1.8 GWh from a single day shift, for example where night shifts are costly or hard to staff.
  • Check the utilities early. The step from 3,000 to 5,500 L/min of compressed air usually means a larger compressor and dryer, and the extra 50 kW must fit the plant’s supply.
  • Check the cell. Both sheets are written around 314 Ah cells. For 500 Ah-plus cells, see 500 Ah-plus cells and ask for a station-by-station check.

To test other run times and OEE values, use the configurator.

Other battery lines from the same supply chain

The same project team also quotes:

  • EV prismatic cell-to-pack (CTP) welding line: 10–15 packs an hour, cells 120–300 mm high, 50–200 mm wide and 20–100 mm thick, fiber laser welding at 3000–4000 W, 80 × 12 × 4 m and 200 kW.
  • 4695 cylindrical cell test and loading station: at least 10 PPM, 2D code scanning, OCV and AC internal-resistance testing with automatic NG sorting, robotic loading of 288-cell pallets, one operator, 2.4 × 1.9 × 2.3 m.
  • Automatic battery laser welding workstation: single-module 6000 W fiber laser, 300 × 500 or 400 × 500 mm X/Y travel, vision positioning, height measurement and in-process weld monitoring.

Send us your cell, module drawing and target output, and we will tell you which line fits and what it needs from your plant.

Questions buyers ask

01

What does 15 PPM mean on a module line?

Fifteen cells per minute, one cell every 4 seconds. With a 1P13S module of 314 Ah cells that is one module about every 52 seconds, against about 97.5 seconds at 8 PPM.

02

Does the faster line need many more people?

No. The 8 PPM line is specified at about 21 operators per shift and the 12–15 PPM line at 19–21. The faster line automates more of the module welding section, so cell processing and module work need 7 operators instead of 9, and it puts 12–14 people in PACK assembly.

03

Can the 15 PPM line run 587 Ah cells?

Its specification is written for 314 Ah prismatic cells. The 8 PPM line is designed for 314 Ah with planned compatibility for 587 Ah cells. Larger cells change fixtures, grippers and station times, so ask for a check against your cell's data sheet.

04

How much does a 15 PPM line cost?

The 8 PPM line starts at RMB 2 million for the base configuration. A 12–15 PPM line has more automated stations and is quoted to your cell, module and plant; send us your cell model, module layout and target output for a quotation.

Related pages

Prices, takt figures and parameters here are typical industry ranges for early planning and comparison; your configuration and quote come from a project proposal.

More guides

Lines, machines and key components —
one point of contact.

Beyond our own line, we run supply-chain solutions for ESS production: sorting, welding, test, logistics and MES equipment and key components, matched to your cell, capacity and budget, delivered and commissioned as one project.

WhatsApp