FAQ

Frequently asked

The questions buyers, process and equipment engineers ask first. Every line figure comes from the proposal; acceptance, lead time, warranty and payment follow below.

01

How is the 8 PPM takt defined?

Takt is counted in cells: 8 cells per minute, or one cell every 7.5 seconds. With the 1P13S reference module that is one module about every 97.5 seconds.

02

What does the line cost?

Prices start at RMB 2 million and depend on line specification, equipment configuration and quantity, with no upper limit. RMB 2 million buys the base configuration, run by about 21 operators with automatic and manual stations; adding MES, logistics and automation takes it to about RMB 3–5 million, and a fully automatic GWh-scale line typically costs RMB 12–40 million or more in China, so prices per GWh are not comparable. At the ECB reference rates of 13 November 2026, RMB 2 million is about US$300,000 or €271,000. Share your cell format, target capacity and plant data for a matching configuration and quote.

03

Which cell, module and PACK sizes are supported?

The reference cell is 314 Ah (207 H × 173 W × 72 T mm, ±0.5 mm), and the design anticipates 587 Ah cells. Modules: 100–240 mm high, 150–370 mm wide, 300–1000 mm long. PACKs: 100–250 mm high, 300–800 mm wide, 600–1200 mm long.

04

How many operators does the line need?

About 21: three in cell processing (1 loading, 2 adhesive), six in module stacking and welding (2 strapping, 1 busbar placement, 1 post-weld cleaning, 1 transfer, 1 reserve) and about twelve in PACK assembly.

05

What does the plant need to provide?

A 55 × 9 × 3.5 m footprint (excluding storage and aisles, adaptable to your building), floor load ≥800 kg/m², 380 V ±5 % 50 Hz three-phase five-wire power at 250 kW rated, compressed air at 0.5–0.7 MPa and ≥3000 L/min, and nitrogen at 0.5 MPa and 40 L/min.

06

What does "≥99 % yield" cover?

Line yield of at least 99 % counts defects caused by the equipment only; operator-induced defects are excluded.

07

Which operations are automated?

Automated: depalletizing, cell test and sort, terminal addressing and polarity check, busbar laser welding, module EOL and thermal adhesive dispensing. Semi-automatic: pressing and strapping, cooling-plate leak test, PACK EOL and full-pack leak test. The remaining stations are manual or assisted.

08

What are the laser-welding quality figures?

A 6 kW galvo laser welds at 50–100 mm/s with ≥1.0 mm penetration, ≥1.5 mm width and ≥1000 N pull strength. Cylinder-driven single-point clamping suits both single- and double-row modules.

09

Can the line connect to MES?

Yes. For example, the adhesive dispenser reports pressure and dispensed volume to MES over Profinet and other protocols. Interfaces are confirmed per project.

10

Who is Stratavolt, and why is the address ctne?

Stratavolt (叠川) is an independent Wuhan brand of energy-storage module and PACK lines. ZeroLine is its exclusive international sales and service partner and handles quotes, contracts, shipping and support outside China. “ctne” in the address is the project’s original code name, kept so existing links keep working. Stratavolt is not connected with other companies that use the name, such as Stratavolt Solutions (stratavoltsol.com) or Stratavolt Group Ltd in the UK.

11

Can the layout be adapted to our building?

Yes. 55 × 9 × 3.5 m is the reference layout; the actual footprint is adapted to your building.

Acceptance, lead time, warranty and payment

Figures marked typical or common are market norms; the schedule, warranty and payment terms for your line are the ones in your quotation and contract.

01

How is the line accepted, and what happens at FAT and SAT?

Twice. The factory acceptance test (FAT) runs in Wuhan before anything is crated, against a checklist and numeric limits written into the contract beforehand: output and takt over a long continuous run, first-pass yield, weld and EOL results, safety functions and documents, with your cells where possible. You attend or watch live on video, and your own engineers or an inspection company you appoint are welcome. The line is crated only after you sign the record; a failed check goes on a fix list and is retested. The site acceptance test (SAT) follows installation at your plant, with your utilities and materials, and the open punch list is closed before the final payment. Use the site acceptance test (SAT) checklist to write those checks down.

02

How long from order to the first pack?

For an export line, factory acceptance typically comes 3–4 months after order, later than in China because of 60 Hz and voltage changes, export documents and trials with your cells. Dismantling and crating take about 2–4 weeks, sea freight and customs about 15–30 days, and installation and commissioning about 10–20 days, so the first pack typically comes off the line 5–6 months after order. Site acceptance and ramp-up take about another 35–70 days: rated output about 7–9 months after order, or 12–18 months if the building itself is new. These are typical durations; your quotation states the schedule for your configuration.

03

Are installation, commissioning and training included?

Yes. Engineers install and commission the line on your site, run it to the output and quality in the contract for site acceptance, and train your operators, maintenance staff and process and quality engineers until it runs at rate; your team can also train on running lines in Wuhan before start-up. Field engineers work in English. For export projects, the engineer days on site and travel costs are listed separately in the quotation, so you can compare them line by line.

04

What warranty comes with the line?

The warranty period and what it covers are written into the contract; for production lines bought in China, one year is typical. During the warranty, faulty parts are replaced free of charge. Wear parts and consumables are listed separately in the quotation and are not covered. Domestic contracts commonly hold back 10 % of the price until the warranty ends.

05

How are spare parts and after-sales support handled?

Every line ships with a recommended spare-parts list, and the critical spares are agreed and quoted before shipping; some tenders require spares worth at least 2 % of the equipment price. When something stops, the engineers who built the line diagnose it by video call, or by remote access where your IT allows, then send the part from regional stock or Wuhan, or arrange a site visit. Response times are written into the contract, and support continues for the working life of the line, including retrofits and new fixtures when you change cell or module format.

06

What are the payment terms?

In China, lines like this are commonly paid 30/30/30/10: 30 % advance, 30 % on shipment after factory acceptance, 30 % after final acceptance and 10 % after the warranty period. Export orders usually pay more before shipment: a deposit at order and the main payment after a passed FAT, before shipping, with a retention after commissioning on your site. Letters of credit at sight or usance are accepted, and deferred terms insured by Sinosure, China’s state export credit insurer, are possible subject to approval of your company’s credit. The split is agreed per project.

Glossary

PPM
Pieces per minute; counted in cells on this line.
OCV
Open-circuit voltage, used to grade and sort cells.
EOL
End-of-line test before a unit leaves the line.
FAT
Factory acceptance test, run at the supplier’s factory before shipping.
SAT
Site acceptance test, run at your plant after installation.
CCS
Cell contact system: busbars and sensing harness on one carrier.
1P13S
One parallel, thirteen series: thirteen cells connected in series.
MSD
Manual service disconnect.
BMS
Battery management system.

Put 55 metres of line
into your plant.

Share your cell spec, module design and plant constraints. Our engineers will come back with a layout and configuration.